10% Lumpsum Provision for Development of North Eastern States
This is a Centrally Sponsored Scheme formulated especially for development of the North Eastern states for which Government of India has earmarked 10% for all Ministries' Budget. It is mainly focused on Development of Urban Infrastructure such as roads, drainage, water supply, solid waste management, etc., Slum Improvement, Poverty Alleviation, etc. The funding pattern is on the basis of 90% central share and 10% state share.
So far 33 projects for development of urban infrastructure in various towns of the State have been sanctioned under this scheme, most of which have been completed and the rest in various stages of completion.
The list of projects sanctioned with status are as under:
STATUS OF PROJECTS ( MORE THAN 50.00LAKHS) IMPLEMENTED UNDER URBAN DEVELOPMENT DEPARTMENT, NAGALAND, KOHIMA | ||||||
STATUS AS ON 1-03-2009 | ||||||
Sl. No | Name of Scheme/Project | Source of Funding |
Total Project cost (Rs. In lakhs) |
Date of sanctioned | Status | Name(s) of Contractors |
1.IMPLEMENTING AGENCY;- URBAN DEVELOPMENT DEPARTMENT NAGALAND | ||||||
1 | Construction of Town Hall at Peren | .CSS -10% LUMP SUM PROVISON FOR DEVELOPMENT OF N.E STATES | 54.89 | 3-2-2004 | Completed | M/S. Pele Khezhie - 144 |
2 | Construction of Cultural Hall at Kohima, Nagaland | 1760.00 |
11-08-2005 |
in progress | M/S VASCON Cl-I - Contractor | |
3 | Construction of Pedestrian Footbridges at Kohima | 165.33 |
10-08-2005 |
in progress |
Dzieseko & Co -323 & Capital Co-operation -333 |
|
4 | Construction of IAS Transit Accomodation, Kohima | 102.00 |
03-02-2004 |
Completed | M/S Capital Co-operation -333 | |
5 | Construction of Amenity Centre at Chumukedima Gate Dimapur. | 140.78 |
24-11-2004 |
Completed | M/S Trident Enterprises - 158 | |
6 | Construction of Amenity Centre at Tsiesema | 76.39 |
24-11-2004 |
Tendering process in progress | ||
7 | Construction of Market Complex at Wokha | 130.58 |
25-11-2003 |
Completed |
1. M/S P. MHA-Jum & Co. 2.M/S BENRIO |
|
8 | Construction of Market Complex at Jalukie | 56.65 |
27-11-2003 |
Completed | M/S Denise Zeliang -120 | |
9 | Construction of Foot path and foot steps at Mon Town | CSS -10% LUMP SUM PROVISON FOR DEVELOPMENT OF N.E STATES | 267.93 | 30-08-2005 | Completed | M.S C.Akai.Toalem Cl-I 354 |
10 | Consructiotn of Retaining wall and protection wall at Longleng Town | 276.00 | 30-3-2006 | in progress | M/S. DENANG PHOM CL-I | |
11 | Construction of Car parking cum Shopping Complex at Mokokchung. | 2194.00 | 24-3-2006 | in progress | M/S, Aien meren Enterprises Cl-I | |
12 | Construction of retaining wall works at Alempang ward Mokokchung | 226.88 | 16-10-2006 | in progress | M/S. PANGER AO CL-I | |
13 | Protection and infrastructure development work at Mokokchung | 825.00 | 17-10-2006 | in progress | M/S. MODERN CONSTRUTCION. CL-I | |
14 | Constn of Shopping Complex cum Car parking at Tamlu. | 932.00 | 29-03-2008 | in progress | M/s lija Construction Cl-I Contractor. | |
15 | Constn of City Shopping mall cumCar parking Complex at New Market. Dimapur. | 2232.00 | 29-03-2008 | Work order issued. Works to commence soon | M/S VASCON Cl-I - Contractor | |
16 | Const. Of guest House/Rest House at Chen Town Mon District Nagaland | 145.45 | 29-03-2008 | Work order issued. Works to commence soon | M/s Neingba Konyak Cl-I Contractor | |
2.IMPLEMENTING AGENCY;- PWD HOUSING, NAGALAND | ||||||
1 | Construction of Walo Guest House, Mon | CSS -10% LUMP SUM PROVISON FOR DEVELOPMENT OF N.E STATES | 176.98 |
Dtd 27-11-2003 |
in progress | M/S A. Neangba Konyak - 277 |
2 | Construction of Indoor Stadium at Kipheri | 106.20 |
Dtd 31-12-2004 |
in progress | M/S. C. Levi Sangtam -358 | |
3 | Construction of Zunheboto College Hostel Building, Zunheboto | 66.61 |
Dtd 23-02-2005 |
Completed | M/S. East West Construction -305 | |
4 | Construction of Zunheboto College Academic Building | 112.55 |
Dtd 24-11-2004 |
Completed | M/S. Toniho Yeptho | |
5 | Construction of Pedestrian Footbridge Mokokchung. | 50.20 |
Dtd 24-08-2005 |
Work to commence soon | M/S. LIMA AO. CL-I | |
6 | Construction of Town Hall at Pfütsero | 50.00 |
Dtd 9-2-2004 |
in progress | M/S Nagaland Building Pvt Ltd | |
3.IMPLEMENTING AGENCY;- PWD R&B, NAGALAND | ||||||
1 | Widening & Improvement of Roads from Mokokchung town to Noksen Town | CSS -10% LUMP SUM PROVISON FOR DEVELOPMENT OF N.E STATES | 680.13 |
Dtd 11-08-2005 |
Completed | M/S, Aien meren Enterprises Cl-I |
2 | Improvement of Town Roads at Phek | 130.24 |
Dtd 25-08-2005 |
Completed | M/S Vascon | |
3 | Improvement of Town Roads at Mokokchung | 156.28 |
Dtd 24-08-2005 |
Completed | M/S NAGALAND STEEL ENGG CL-I | |
4 | Improvement of Town Roads, Mon | 100.00 |
Dtd 28-11-2003 |
Completed | M/S H.Pujok CL-I | |
5 | Improvement of Town Roads at Noklak | 96.46 |
Dtd 27-11-2003 |
Completed | M/S Guolhoulie Rio CL-I | |
3.IMPLEMENTING AGENCY;- DEVELOPMENT AUTHORITY NAGALAND | ||||||
1 | Construction of Ngwalua Town Circular Road under Peren District, Nagaland | CSS -10% LUMP SUM PROVISON FOR DEVELOPMENT OF N.E. STATES | 380.26 | 09-01-2007 | in progress | Development Authority Nagaland |
2 | Construction of Market complex at Naga Shopping Arcade Dimapur | 336.00 | 09-01-2008 | in progress | Development Authority Nagaland |